“ARE THERE any ghost projects in Taguig?”
So, asked Sen. Alan Peter Cayetano, the gentleman from Taguig, of Public Works Secretary Vince Dizon during the Senate finance subcommittee’s hearing on the budget of the DPWH on Sept. 25.
“None. In our investigation, none,” replied Dizon.
“Poor Vince Dizon. The ‘pressure’ of work may have clouded his memory. The DPWH already turned over to my Senate office records of nonexistent but reported as completed slope protection projects in Taguig,” riposted Sen. Ping Lacson who initiated the digging of what amounted to a mountain of alleged flood control and reclamation anomalies in Taguig, truckloads of documents of which have been turned over to the Ombudsman for investigation.
“Poor DPWH Site Inspection Engineers. Their boss, Sec Vince Dizon directly contradicted their own site inspection reports in Taguig, specifically submitted by personnel from the department’s Bureau of Quality and Safety and Bureau of Maintenance,” Lacson added. And there’s more coming from the intrepid senator.
On Sept. 27, he asked in a post on X: “Sec. Vince Dizon, please explain how this finding of your own team should not be flagged as a ghost project in Taguig. Since when has Taguig been located in Leyte?”
This, he backed with a report on a Taguig project with Contract ID 220B0106, whose geotagged photographs attached to its billing reports contained coordinates “located approximately 600 kilometers away in Leyte province.”
Lacson cited project’s financial billing documents that showed that a 15% advance payment of P13,738,755.81 was released on June 23, 2022, with all the attached billing photographs bearing coordinates in Tacloban City, Leyte.
Amounting to P37.162 million, the first partial billing was dated July 27, 2022, but had no image attached. The second partial billing, amounting to P19.174 million and dated Sept. 12, 2022, had attached images with no coordinates. The third partial billing, amounting to P21.202 million and dated Sept. 22, 2022, also did not have coordinates in its attached images. The fourth and final billing, amounting to P18.960 million and dated Feb. 22, 2023, likewise had attached images without coordinates.
Lacson noted that the DPWH inspection report also found that the coordinates indicated in the geotagged photographs attached to the Progress Billing and Final Billing “do not correspond with the actual project site verified during the inspection.”
“To further highlight the red flag, Discaya’s St. Timothy is the contractor. What do you say about this, Sec?” Lacson added, referencing to spouses Curlee and Sarah Discaya, the poster couple of the anomalous multibillion-peso flood control projects that exploded into the national consciousness last year.
No ghost projects in Taguig.
Convince us Sec Vince, please, as you did when you said there were no anomalies in the preparation and holding of the 30th Southeast Asian Games in 2019 at the then-your domain, New Clark City, notwithstanding Cayetano’s infamous P50-M kaldero, now passed NBI investigation, and corresponding charges ready for filing. With PDI reports/Grafix: MB