Home Headlines SBMA starts P442.7-M Magsaysay bridge project

SBMA starts P442.7-M Magsaysay bridge project

2174
0
SHARE

Pedestrians monopolize traffic at the Magsaysay Bridge leading to the Subic Bay Freeport main gate since the span was closed to vehicles in 2009. Notice the park bench bolted on the surface of the span to serve as rest area for pedestrians. Photo by Malou Dungog

SUBIC BAY FREEPORT — The much-awaited project to replace a US Navy-era bridge that serves as the major connection between the Subic Bay Freeport Zone and Olongapo City is now underway, 10 years after the concrete span was closed to vehicular traffic due to deterioration.

Subic Bay Metropolitan Authority (SBMA) chair and administrator Wilma T. Eisma said the agency has allocated P442.7 million to build a fourlane span to replace the twolane Magsaysay Bridge, as well as improve the Main Gate security facilities and upgrade road network, drainage structures and signage in the immediate area.

The project, which is expected to be finished by the first quarter of 2021, is designed to improve access and mobility, revitalize business in the area, and generate more opportunities for local livelihood.

“Aside from improving accessibility to the Subic Bay Freeport because this connects to the main artery in Olongapo, which is the Magsaysay Drive and Rizal Avenue, this project also takes into consideration public safety and convenience because the bridge is heavy in foot traffic,” Eisma pointed out.

“It also reflects our preparations for the boom in local tourism business, as this will improve the appearance of the Main Gate, which used to be the iconic symbol of Subic since when it became a naval base,” she added.

The project, which will be undertaken by the consortium of Front Nine Konstruct Builders & Realty Development Corp., Qingdao Municipal Construction Group Co., Ltd., and Rebcor Construction and Trading Corp., is part of the agency’s rebuilding thrust to sustain Subic as an investment hub and center of economic growth.

Recently, the SBMA announced a P1.6-billion program to repair ageing facilities constructed when Subic was still an American naval base, a badly-needed upgrade, Eisma said.

“For almost two decades now, the Navy-era facilities in Subic remained as they were. We’re now fixing these because the better our facilities are, the more businesses and jobs we can generate,” she said.

The deterioration of the Magsaysay Bridge, which was built by the US Navy in the early ‘60s, was detected as early as 1999 when experts restricted its maximum load capacity to 20 tons. The bridge was eventually closed to vehicular traffic in 2009.

However, actual construction was put on hold over the years due to budget constraints and it was only last year that the SBMA funded a new detailed engineering design for a new structure.

According to the SBMA Engineering Department, the new Magsaysay Bridge will be a 72.5-meter multi-span slab bridge, about 600 mm thick on the average and with a total carriage width of 24.15 meters. It will also have a covered walkway for pedestrians.

The bridge project will also involve the demolition and removal of the existing two-lane span; construction of security gate and fence at the Main Gate; and building of a new covered walkway from Magsaysay Bridge to the intersection of Rizal Highway, which is a major road in Subic’s central business district.

The package will also include construction of new intersection and road expansion in the Main Gate area; building of drainage structures; and relocation of existing facilities for power, water, sewerage and telecommunications.

As of now, the contractor is starting work on the foundations for a temporary pedestrian bridge that will be built before the existing bridge is demolished.

The new Magsaysay Bridge is expected to be finished within 540 calendar days, Eisma said.

LEAVE A REPLY

Please enter your comment!
Please enter your name here